Who handles Sigora Solar accounts now

Sigora no longer operates and no company has been reported as taking over its customers. If you financed your system, keep paying and contact the company that bills you. Panel and inverter warranties remain with the manufacturers, and a licensed local contractor can service your system.

What it means for homeowners

  • Sigora's workmanship warranties are no longer being honored because the company stopped operating in September 2023.
  • If you won a court judgment against Sigora, ask Virginia DPOR whether you qualify for the Contractor Transaction Recovery Fund.
  • The Virginia Attorney General's office has received complaints about Sigora; you can file one too.
  • WMRA described Sigora as being in bankruptcy, but we could not find the court case, so check before relying on a bankruptcy claim process.
  • Keep paying any solar loan; the lender is a separate company from Sigora.

Dealing with Sigora Solar?

Tell us what happened. It takes about two minutes, and you decide what happens next.

See my options

Timeline

2011

Founded by Bogdan "Andy" Bindea as a Waynesboro, Virginia solar installer.

2017

Business filings showed a new CEO and a move of the principal office to Charlottesville.

July 2021

Fairfax County ended its solar contract with Sigora about 18 months early.

November 2022

Sigora cut nearly half its workforce, including its CEO.

Summer 2023

A new CEO took over and the principal office moved to Staunton; the Staunton landlord evicted the company in August 2023.

September 2023

Sigora ceased all operations, according to an internal email reported by WMRA.

January 2025

WMRA reported 16 lawsuits in eight courts in which Sigora was found liable to customers and partners, with judgments totaling $2.9 million, including judgments for customers who prepaid for installations that were never finished.

Official contacts

Virginia DPOR Contractor Transaction Recovery Fund

Virginia consumers with a court judgment against a licensed contractor that went out of business may be eligible to file a claim.

WMRA investigation, Jan 22, 2025

Detailed reporting on Sigora's closure, lawsuits, and unpaid judgments.

Your options

Sources

  1. WMRA, Jan 22, 2025. 2011 founding, office moves, November 2022 layoffs, September 2023 closure, 16 lawsuits with $2.9 million in judgments, Recovery Fund, AG complaints.
  2. Virginia DPOR Contractor Transaction Recovery Fund. Official Recovery Fund page.

About this profile.

Solar Accountability is independent of Sigora Solar. This page reports public facts from the sources listed and is not legal advice. If something here is out of date, please let us know.